The Ontario Building Code | Quantity of Materials

9.26.11.1. Quantity of Materials

(1) The quantities of bituminous materials used on built-up roofs shall conform to Table 9.26.11.1.

Table 9.26.11.1.
Quantities of Bitumen for Built-Up Roofs

Forming Part of Sentence 9.26.11.1.(1)

Item

Column 1

Column 2

Column 3

Type of Roof

Amount of Bitumen per Square Metre of Roof surface

Mopping Coats Between Layers

Flood Coat

1.

asphalt and aggregate

1 kg

3 kg

2.

Coal-tar and aggregate

1.2 kg

3.6 kg

3.

Cold process roofing

0.75 L cold process cement

2 L cold process top coating